Development Update August 28th

Hereford Watermain:

All watermain work is complete. In Hereford St. and on-site. We also understand that the City has completed road repairs on Hereford where they were doing their watermain repair work.

 

Paving:

Castle Contracting has completed the paving of all alleys. Paving of the Wilson extension entrance to the project has been completed. Street paving of the main N-S street (Boardman) has begun.

 

Grading:

Only fine grading of the detention areas remains. Fine grading of the single family home lots will be completed as each home is constructed.

 

Sewers:

Castle has installed all sanitary and storm sewers. The green pipes you see sticking up on site are in the alleys and are for each single-family home.

 

Ameren Electrical Service:

New electric service has been brought into the site on poles from the North-East (near Ragazzi’s) and on the South on Bischoff. Castle has started installing the underground conduit distribution system for all areas of the project. One utility pole remains to be relocated behind Imo’s Meats. This will allow for the completion of the alley paving connection to Daggett in this area. Ameren crews will begin pulling service wire through the installed conduit and placing transformer on the site within the next two weeks.

 

Storm Water Detention Areas:

With the paving of the streets and alleys, storm water has begun to flow to the detention areas, improving overall site drainage. Grass sod will soon be installed in each storm water detention area.

 

Street Lighting:

City streetlight poles have been ordered by Castle Contracting. Installation will begin in mid-September.

2019-08-28T15:56:34+00:00