Development Update October 11

Watermains:

All work is complete. The City still needs to complete some street repairs on Hereford and Daggett. Castle Construction has been told by the City that the street repairs related to this work is scheduled, however a date has not been given.  We are aware that some of these depressions are significant and have asked Castle to call the City weekly about this topic until the repaving is completed.

 

Paving:

On-site street paving is 100% complete. A City inspection of the site work went well this week with no significant punch-list items.

 

Grading:

Most grading is complete. Backfilling around new roads and alleys remain. Fine grading of the single-family home lots will be completed as each home is constructed.

 

Sewers:

Most sewer work is complete. The green pipes you see sticking up on site are in the alleys and are for each single-family home.

 

Ameren Electrical Service:

Ameren is approximately 90% done with pulling all electrical service wire to each home lot within the development.

 

Spire Gas Service:

Spire is starting installation of gas services to each lot next week. The always follow Ameren’s work.

 

Storm Water Detention Areas:

With the paving of the streets and alleys, storm water is now flowing to the detention areas, improving overall site drainage. Grass sod has been installed in each of the detention areas in order to stabilize the soil slopes. Fall protection fencing is being installed on the tops of all the detention area retaining walls. This work will be completed next week.

 

Street Lighting, and Communications Cabling:

Installation of the electric conduit for the street lighting has begun. The light poles will begin installation in a few weeks. The streetlight pole is the same as is used throughout The Hill neighborhood, in keeping with the extension of the neighborhood idea.