Development Update Nov 7th

Watermains:

All work is complete. The City has now completed paving repairs on Hereford and Daggett.

 

Paving:

On-site street paving is 100% complete.

 

Grading:

Most grading is complete. Backfilling around new roads and alleys remain. Fine grading of the single-family home lots will be completed as each home is constructed.

 

Sewers:

Sewer work is complete. The green pipes you see sticking up on site are in the alleys and are for each single-family home.

Ameren Electrical Service:

Ameren is approximately 95% complete.

Spire Gas Service:

Spire gas line installation is approximately 75% complete.

Storm Water Detention Areas:

The storm water detention areas are 100% complete.

 

Street Lighting, and Communications Cabling:

Installation of the electric conduit for the street lighting has begun. The light pole installation work will begin during the week of 11/15.  The streetlight pole is the same as is used throughout The Hill neighborhood, in keeping with the extension of the neighborhood idea.